The failure costs you collected in Lesson 2 are the visible part. Quality engineers describe the full cost as an iceberg: scrap, rework, and warranty float above the water where accountants can see them, and a larger mass sits below. Hidden costs include overtime to retest a reworked batch, expedited freight to replace a rejected shipment, engineering hours spent on complaint investigations, lost capacity while a line is held for disposition, excess inventory kept as a cushion against defects, and customers who quietly stop ordering.
Hidden costs rarely have their own ledger line. They are buried in overhead, overtime, freight, and salaried time. Finding them means asking people what they did last week because of a defect and putting an hourly rate on it. You will not capture everything, and you do not need to. Capturing even half of the hidden cost usually changes the priority list.
A practical approach is to pick one significant failure event and trace every cost it caused for two weeks. The ratio of hidden to visible cost from that trace can then be applied as a rough multiplier to the monthly visible figure until better tracking exists.
Standard Procedure
- 1List the visible failure costs already collected for the period.
- 2Interview production, logistics, engineering, and customer service about work caused by defects.
- 3Put hours and rates or invoice values against each hidden item.
- 4Add hidden items to visible costs and report the hidden share as a percentage.
Lesson Summary
- ✓Hidden costs do not appear on scrap tickets; you have to go ask for them.
- ✓Even a partial trace of hidden cost typically adds 30 percent or more to the visible figure.