FPY only works if the counts are captured where the failure happens. The simplest system is a rework tag: whenever an operator or inspector finds something that must be corrected, they fill in a tag with the station, the reason from a fixed short list, and the time. The tag travels with the unit to the repair bench and is dropped in a box there. Entering count comes from the production schedule or a counter at the station.

At the end of each shift someone counts the tags per station, subtracts from the entering count and posts the FPY on a board by the line. A one-week trend chart beside it shows whether things are getting better or worse. A sudden drop of a few points in one day is a signal, not noise, when the volume is in the thousands.

Sorting the tag reasons from most to least frequent for the weakest station gives the improvement team its first target. Error-proofing the top reason, such as a tape-width check at the dispenser, usually recovers more yield than any amount of retraining.

Key Concept
Rework tags filled in at the point of failure give you per-station FPY and the reason ranking in one step.
Practical Example
In one week the taping station received 2,400 harness bundles. The tag box held 72 tags: 41 for loose tape wraps, 19 for wrong tape width and 12 for a missed branch. FPY = (2,400 − 72) ÷ 2,400 = 2,328 ÷ 2,400 = 0.97, or 97.0 percent. The station target is 98.5 percent. Loose wraps are 57 percent of the tags, so tension setting on the taping heads is the first thing to check.

Standard Procedure

  1. 1Issue a rework tag for every unit that needs correction, with station and reason code.
  2. 2Count tags per station at shift end and subtract from units entering to get first-time-good.
  3. 3Post FPY per station on a board with a one-week trend.
  4. 4Rank the tag reasons for the lowest station and assign the top reason to the improvement team.
  5. 5Recheck the FPY one week after the fix to confirm the gain held.

Lesson Summary

  • ✓Capture rework at the point of failure, not from memory at the end of the shift.
  • ✓The reason ranking on the tags is the action list for the improvement team.

Progress Tracking

Sign in to save your lesson completion markers.

🎉 You have reached the final lesson of this course!

When you feel confident with the material, proceed to the final assessment to test your knowledge and earn your certificate.